# Milestones
What it is: Zero-duration checkpoints (e.g., Kickoff, Launch) that stand out on the timeline.
- Click + Add task and name it (e.g., βGo-Liveβ).
- Set Start = End (or toggle Milestone where available) β Save.


- Good to know: Use color π¨ to categorize milestones (e.g., approvals vs. releases).
β What it is What it is β